Hunter Electrical Opportunity Report

Every development application, complying development certificate and construction certificate lodged with the five Hunter councils in the fortnight to 10 September 2026 — scored, filtered, and turned into a call list.

Coverage Newcastle · Lake Macquarie · Maitland · Port Stephens · Cessnock Period 27 August 2026 to 10 September 2026 Source NSW Planning Portal ePlanning open data (CC-BY)
New or updated
1,107projects across five councils in the 14 days to 10 Sep
Worth acting on
157 high priority, 8 medium — the rest is filtered out for you
Verified construction value
$1.22bndeclared cost, cross-checked against floor area and dwelling counts
Estimated electrical share
$93.9m+range $93.9m – $160.5m; an estimate, not a quote
Builders named
126certificates that name the building company, so you know who to ring

Ring these this week

11 projects · certificate stage

These have passed the certificate stage, which means the builder is appointing trades right now or has just done it. This is the shortest window in the whole pipeline and the only section where a phone call this week changes the outcome. Where the certificate names the building company, we have printed it.

01 Commercial
100score

Mixed use development (280 dwellings), Newcastle West

309 King Street Newcastle West 2302 · Newcastle

Construction certificate lodged · Under Assessment · updated 9 Sep Cross-checked

Declared cost
$80,300,000
Electrical opportunity
$7.2m – $12.0m (9–15% est.)
Dwellings
280
Storeys
16
From Newcastle CBD
2 km

Builder on the certificateGWH BUILD PTY LTD

Likely electrical scope

  • Main switchboard and distribution
  • LED lighting and controls
  • Data cabling and comms
  • Base-build and tenancy metering
  • EV charging infrastructure
  • Access control, CCTV and intercom
  • Mechanical services power
  • Emergency and exit lighting

What to do about it

Call within 2 weeks CC is lodged, so the builder is pricing and awarding packages. This is the last clean window to get on the tender list.

Who: GWH BUILD PTY LTD — site manager or contracts administrator

Why it scored

  • Builder named in the certificate
  • 280 dwellings
  • Commercial/industrial BCA class
CFT-1024947 NSW Planning Portal reference · verify on the council DA tracker before quoting
02 Commercial
100score

Shop top housing, Newcastle West

924 Hunter Street Newcastle West 2302 · Newcastle

Construction certificate lodged · Under Assessment · updated 2 Sep Plausible

Declared cost
$6,565,956
Electrical opportunity
$591k – $985k (9–15% est.)
Lots
194
From Newcastle CBD
2 km

Builder on the certificateDECODE CONSTRUCTION PTY LTD

Likely electrical scope

  • Main switchboard and distribution
  • LED lighting and controls
  • Data cabling and comms
  • Base-build and tenancy metering
  • EV charging infrastructure
  • Access control, CCTV and intercom
  • Mechanical services power
  • Emergency and exit lighting

What to do about it

Call within 2 weeks CC is lodged, so the builder is pricing and awarding packages. This is the last clean window to get on the tender list.

Who: DECODE CONSTRUCTION PTY LTD — site manager or contracts administrator

Why it scored

  • Builder named in the certificate
  • Commercial/industrial BCA class
  • 194 lots
CFT-1006885 NSW Planning Portal reference · verify on the council DA tracker before quoting
03 Government Education
95score

Centre-based child care, Boolaroo

5 Lakeview Street Boolaroo 2284 · Lake Macquarie

Construction certificate issued · Determined · updated 8 Sep Cross-checked

Declared cost
$3,294,500
Electrical opportunity
$362k – $560k (11–17% est.)
Proposed floor area
633 m²
Storeys
1
From Newcastle CBD
15 km

Builder on the certificateBROWN COMMERCIAL BUILDING PTY LIMITED

Likely electrical scope

  • Classroom lighting and controls
  • Data cabling and AV
  • Switchboard upgrades
  • Emergency and exit lighting
  • Solar PV
  • Security, CCTV and access control
  • Air conditioning power
  • Child-safe outlets and compliance

What to do about it

Call this week Construction certificate is issued. Trades are being locked in now or have just been locked in. Ask who holds the electrical package and whether they need a second crew for programme relief.

Who: BROWN COMMERCIAL BUILDING PTY LIMITED — site manager or contracts administrator

Why it scored

  • Builder named in the certificate
  • Commercial/industrial BCA class
CFT-1018137 NSW Planning Portal reference · verify on the council DA tracker before quoting
04 Government Education
92score

Centre-based child care, Argenton

415 Lake Road Argenton 2284 · Lake Macquarie

Construction certificate lodged · Under Assessment · updated 1 Sep Plausible

Declared cost
$2,158,552
Electrical opportunity
$237k – $367k (11–17% est.)
From Newcastle CBD
14 km

Builder on the certificateThe Trustee for Vivid ELS Properties 3 Unit Trust

Likely electrical scope

  • Classroom lighting and controls
  • Data cabling and AV
  • Switchboard upgrades
  • Emergency and exit lighting
  • Solar PV
  • Security, CCTV and access control
  • Air conditioning power
  • Child-safe outlets and compliance

What to do about it

Call within 2 weeks CC is lodged, so the builder is pricing and awarding packages. This is the last clean window to get on the tender list.

Who: The Trustee for Vivid ELS Properties 3 Unit Trust — site manager or contracts administrator

Why it scored

  • Builder named in the certificate
  • Commercial/industrial BCA class
CFT-995972 NSW Planning Portal reference · verify on the council DA tracker before quoting
05 Residential New residential
91score

Residential flat building, Nelson Bay

90 Magnus Street Nelson Bay 2315 · Port Stephens

Construction certificate issued · Determined · updated 9 Sep Cross-checked

Declared cost
$5,453,572
Electrical opportunity
$327k – $545k (6–10% est.)
Proposed floor area
711 m²
Storeys
4
From Newcastle CBD
41 km

Builder on the certificateHPAC PTY LTD

Likely electrical scope

  • Full rough-in and fit-off
  • Switchboard and metering
  • LED lighting and fans
  • Data and TV cabling
  • Solar PV and battery
  • EV charger provision
  • Smoke alarms
  • Air conditioning power

What to do about it

Call this week Construction certificate is issued. Trades are being locked in now or have just been locked in. Ask who holds the electrical package and whether they need a second crew for programme relief.

Who: HPAC PTY LTD — site manager or contracts administrator

Why it scored

  • Builder named in the certificate
  • Commercial/industrial BCA class
CFT-1025955 NSW Planning Portal reference · verify on the council DA tracker before quoting
06 Industrial
91score

Light industry, Gateshead

51 Oakdale Road Gateshead 2290 · Lake Macquarie

Construction certificate issued · Determined · updated 2 Sep Plausible

Declared cost
$2,984,500
Electrical opportunity
$298k – $537k (10–18% est.)
Storeys
2
From Newcastle CBD
10 km

Builder on the certificateSafetybuild

Likely electrical scope

  • Three-phase distribution and switchboards
  • High-bay lighting
  • Machine and plant power
  • Solar PV and metering
  • EV and forklift charging
  • Data cabling and comms racks
  • Fire and emergency systems

What to do about it

Call this week Construction certificate is issued. Trades are being locked in now or have just been locked in. Ask who holds the electrical package and whether they need a second crew for programme relief.

Who: Safetybuild — site manager or contracts administrator

Why it scored

  • Builder named in the certificate
  • Commercial/industrial BCA class
CFT-1014577 NSW Planning Portal reference · verify on the council DA tracker before quoting
07 Commercial Retail
84score

Retail Premise (2 dwellings), Cooranbong

266 Newport Road Cooranbong 2265 · Lake Macquarie

Construction certificate issued · Determined · updated 1 Sep Plausible

Declared cost
$2,750,000
Electrical opportunity
$275k – $440k (10–16% est.)
Dwellings
2
Proposed floor area
246 m²
Storeys
1
From Newcastle CBD
32 km

Builder on the certificateBULLSEYE CONSTRUCTION NSW PTY LTD

Likely electrical scope

  • Tenancy fitout distribution
  • Feature and display lighting
  • Refrigeration and kitchen power
  • POS and data cabling
  • Signage power
  • Emergency and exit lighting
  • CCTV and alarms

What to do about it

Call this week Construction certificate is issued. Trades are being locked in now or have just been locked in. Ask who holds the electrical package and whether they need a second crew for programme relief.

Who: BULLSEYE CONSTRUCTION NSW PTY LTD — site manager or contracts administrator

Why it scored

  • Builder named in the certificate
  • Commercial/industrial BCA class
CFT-1013695 NSW Planning Portal reference · verify on the council DA tracker before quoting
08 Government Education
83score

Centre-based child care, Morisset

4 Stockton Street Morisset 2264 · Lake Macquarie

Construction certificate issued · Determined · updated 9 Sep Plausible

Declared cost
$2,750,000
Electrical opportunity
$302k – $468k (11–17% est.)
Proposed floor area
645 m²
Storeys
2
From Newcastle CBD
34 km

Likely electrical scope

  • Classroom lighting and controls
  • Data cabling and AV
  • Switchboard upgrades
  • Emergency and exit lighting
  • Solar PV
  • Security, CCTV and access control
  • Air conditioning power
  • Child-safe outlets and compliance

What to do about it

Call this week Construction certificate is issued. Trades are being locked in now or have just been locked in. Ask who holds the electrical package and whether they need a second crew for programme relief.

Who: Site manager or contracts administrator at the named builder

Why it scored

  • Commercial/industrial BCA class
CFT-1026394 NSW Planning Portal reference · verify on the council DA tracker before quoting
09 Commercial Retail
82score

Office Premise, Rutherford

15 Spitfire Place Rutherford 2320 · Maitland

Complying development approved · Approved · updated 9 Sep Cross-checked

Declared cost
$8,072,018
Electrical opportunity
$807k – $1.3m (10–16% est.)
Dwellings
1
Storeys
2
From Newcastle CBD
36 km

Likely electrical scope

  • Tenancy fitout distribution
  • Feature and display lighting
  • Refrigeration and kitchen power
  • POS and data cabling
  • Signage power
  • Emergency and exit lighting
  • CCTV and alarms
  • Car park lighting and ventilation controls

What to do about it

Call within 2 weeks Complying development is approved and can start immediately. CDC jobs move fast and often have no electrician appointed.

Who: Owner-builder, project home builder or certifier's client

Why it scored

  • Commercial/industrial BCA class
CDC-380220 16772-01 NSW Planning Portal reference · verify on the council DA tracker before quoting
10 Industrial
82score

Warehouse or distribution centre, Black Hill

16 Viney Creek Drive Black Hill 2322 · Newcastle

Complying development approved · Approved · updated 1 Sep Plausible

Declared cost
$1,700,000
Electrical opportunity
$170k – $306k (10–18% est.)
Storeys
1
From Newcastle CBD
19 km

Likely electrical scope

  • Three-phase distribution and switchboards
  • High-bay lighting
  • Machine and plant power
  • Solar PV and metering
  • EV and forklift charging
  • Data cabling and comms racks
  • Fire and emergency systems

What to do about it

Call within 2 weeks Complying development is approved and can start immediately. CDC jobs move fast and often have no electrician appointed.

Who: Owner-builder, project home builder or certifier's client

Why it scored

  • Commercial/industrial BCA class
CDC-381206 CDC/5710942-A NSW Planning Portal reference · verify on the council DA tracker before quoting
11 Residential New residential
74score

Dwelling house, Warners Bay

91 Warners Bay Road Warners Bay 2282 · Lake Macquarie

Construction certificate issued · Determined · updated 7 Sep Cross-checked

Declared cost
$2,000,000
Electrical opportunity
$120k – $200k (6–10% est.)
Dwellings
1
Proposed floor area
420 m²
Storeys
1
From Newcastle CBD
13 km

Builder on the certificateGraph Builders Pty Ltd

Likely electrical scope

  • Full rough-in and fit-off
  • Switchboard and metering
  • LED lighting and fans
  • Data and TV cabling
  • Solar PV and battery
  • EV charger provision
  • Smoke alarms
  • Air conditioning power

What to do about it

Call this week Construction certificate is issued. Trades are being locked in now or have just been locked in. Ask who holds the electrical package and whether they need a second crew for programme relief.

Who: Graph Builders Pty Ltd — site manager or contracts administrator

Why it scored

  • Builder named in the certificate
CFT-1005641 NSW Planning Portal reference · verify on the council DA tracker before quoting

High and medium priority, further out

4 projects

Approved or progressing, but the trades are not being appointed yet. The play here is a short introduction now so that you are already a name when the package goes out.

01 Commercial
89score

Mixed use development (131 dwellings), Morisset Park

81 Trinity Point Drive Morisset Park 2264 · Lake Macquarie

DA on public exhibition · Under Assessment · updated 3 Sep Cross-checked

Declared cost
$463,012,395
Electrical opportunity
$41.7m – $69.5m (9–15% est.)
Dwellings
131
Lots
10
Storeys
8
From Newcastle CBD
31 km

Likely electrical scope

  • Main switchboard and distribution
  • LED lighting and controls
  • Data cabling and comms
  • Base-build and tenancy metering
  • EV charging infrastructure
  • Access control, CCTV and intercom
  • Mechanical services power
  • Emergency and exit lighting

What to do about it

Register interest now Publicly exhibited, so the project is real and progressing. Early contact is cheap and memorable.

Who: Developer or architect

Why it scored

  • 131 dwellings
  • 10 lots
PAN-657429 DA/1141/2026 NSW Planning Portal reference · verify on the council DA tracker before quoting
02 Industrial
75score

Warehouse or distribution centre, Thornton

31 Glenwood Drive Thornton 2322 · Maitland

Development approved · Determined · updated 9 Sep Plausible

Declared cost
$2,984,505
Electrical opportunity
$298k – $537k (10–18% est.)
From Newcastle CBD
21 km

Likely electrical scope

  • Three-phase distribution and switchboards
  • High-bay lighting
  • Machine and plant power
  • Solar PV and metering
  • EV and forklift charging
  • Data cabling and comms racks
  • Fire and emergency systems

What to do about it

Call within 4-6 weeks Consent is granted. The next step is a construction certificate, which means the builder is being appointed. Get in front of the developer before the builder is chosen and you inherit their sparky.

Who: Developer or project manager named on the DA

PAN-671711 DA/2025/860:1 NSW Planning Portal reference · verify on the council DA tracker before quoting
03 Commercial
74score

Shop top housing (4 dwellings), Merewether

190 Glebe Road Merewether 2291 · Newcastle

Development approved · Determined · updated 3 Sep Cross-checked

Declared cost
$2,579,500
Electrical opportunity
$232k – $387k (9–15% est.)
Dwellings
4
Lots
3
From Newcastle CBD
3 km

Likely electrical scope

  • Main switchboard and distribution
  • LED lighting and controls
  • Data cabling and comms
  • Base-build and tenancy metering
  • EV charging infrastructure
  • Access control, CCTV and intercom
  • Mechanical services power
  • Emergency and exit lighting

What to do about it

Call within 4-6 weeks Consent is granted. The next step is a construction certificate, which means the builder is being appointed. Get in front of the developer before the builder is chosen and you inherit their sparky.

Who: Developer or project manager named on the DA

PAN-669427 MA2026/01274 NSW Planning Portal reference · verify on the council DA tracker before quoting
04 Infrastructure
72score

6-lot subdivision, Floraville

119 Floraville Road Floraville 2280 · Lake Macquarie

Development approved · Determined · updated 1 Sep Plausible

Declared cost
$633,219
Electrical opportunity
$76k – $139k (12–22% est.)
Lots
6
From Newcastle CBD
14 km

Likely electrical scope

  • Street and public lighting
  • Underground reticulation and pits
  • Traffic and ITS power
  • Pump and plant control
  • Earthing systems

What to do about it

Call within 4-6 weeks Consent is granted. The next step is a construction certificate, which means the builder is being appointed. Get in front of the developer before the builder is chosen and you inherit their sparky.

Who: Developer or project manager named on the DA

PAN-646720 DA/1321/2022/A NSW Planning Portal reference · verify on the council DA tracker before quoting

The fortnight in numbers

1,107 projects analysed
Where the money is, by councilVerified construction value this fortnight, then project count.
Newcastle$217.5m · 279Lake Macquarie$627.2m · 340Maitland$158.1m · 222Port Stephens$68.9m · 104Cessnock$145.5m · 162
Where the money is, by sectorResidential dominates by count; commercial dominates by value.
Residential$507.2m · 969Commercial$586.2m · 93Industrial$54.2m · 24Government$42.8m · 16Infrastructure$26.7m · 5
ResidentialCommercialIndustrialGovernmentInfrastructure
Where the fortnight's work sits in the approval pipelineCount of projects, and verified construction value at each step. Later steps mean sooner work.
Under assessment217 · $99.8mOn exhibition59 · $551.4mInfo requested181 · $235.8mDA approved137 · $53.1mCDC lodged78 · $26.5mCDC approved139 · $45.9mCC lodged116 · $128.2mCC issued180 · $76.4m

By sector

score 55 and above

The same fortnight, sorted the way you probably think about your business. Everything below scored 55 or better; the low-value noise — pools, sheds, fences, decks — has been removed.

Commercial 8 shown

ScoreProjectCouncilStage CostElectrical est.Builder
100 Mixed use development (280 dwellings), Newcastle West 309 King Street Newcastle West 2302 Newcastle Construction certificate lodged $80.3m $7.2m – $12.0m GWH BUILD PTY LTD
100 Shop top housing, Newcastle West 924 Hunter Street Newcastle West 2302 Newcastle Construction certificate lodged $6.6m $591k – $985k DECODE CONSTRUCTION PTY LTD
89 Mixed use development (131 dwellings), Morisset Park 81 Trinity Point Drive Morisset Park 2264 Lake Macquarie DA on public exhibition $463.0m $41.7m – $69.5m
84 Retail Premise (2 dwellings), Cooranbong 266 Newport Road Cooranbong 2265 Lake Macquarie Construction certificate issued $2.8m $275k – $440k BULLSEYE CONSTRUCTION NSW PTY LTD
82 Office Premise, Rutherford 15 Spitfire Place Rutherford 2320 Maitland Complying development approved $8.1m $807k – $1.3m
74 Shop top housing (4 dwellings), Merewether 190 Glebe Road Merewether 2291 Newcastle Development approved $2.6m $232k – $387k
63 Restaurant or cafe, Newcastle 220 Hunter Street Newcastle 2300 Newcastle Construction certificate lodged $300k $30k – $48k
62 Retail Premise, Warners Bay 2/337 Hillsborough Road, Warners Bay NSW 2282 Lake Macquarie Complying development lodged $706k $71k – $113k

Industrial 8 shown

ScoreProjectCouncilStage CostElectrical est.Builder
91 Light industry, Gateshead 51 Oakdale Road Gateshead 2290 Lake Macquarie Construction certificate issued $3.0m $298k – $537k Safetybuild
82 Warehouse or distribution centre, Black Hill 16 Viney Creek Drive Black Hill 2322 Newcastle Complying development approved $1.7m $170k – $306k
75 Warehouse or distribution centre, Thornton 31 Glenwood Drive Thornton 2322 Maitland Development approved $3.0m $298k – $537k
68 Industrial development, Rutherford 91 Gardiner Street Rutherford 2320 Maitland Development approved $2.8m $279k – $503k
65 General industry, Heatherbrae 18 Kierman Circuit Heatherbrae 2324 Port Stephens DA on public exhibition $15.0m $1.5m – $2.7m
65 General industry, Williamtown 31 Aerospace Avenue Williamtown 2318 Port Stephens DA on public exhibition $10.9m $1.1m – $2.0m
64 Warehouse or distribution centre, Mayfield North 151 Ingall Street Mayfield North 2304 Newcastle DA under assessment $2.2m $225k – $405k
60 General industry, Maryland 19-21 Carbine Close Maryland 2287 Newcastle DA under assessment $1.8m $176k – $317k

Government 5 shown

ScoreProjectCouncilStage CostElectrical est.Builder
95 Centre-based child care, Boolaroo 5 Lakeview Street Boolaroo 2284 Lake Macquarie Construction certificate issued $3.3m $362k – $560k BROWN COMMERCIAL BUILDING PTY LIMITED
92 Centre-based child care, Argenton 415 Lake Road Argenton 2284 Lake Macquarie Construction certificate lodged $2.2m $237k – $367k The Trustee for Vivid ELS Properties 3 Unit Trust
83 Centre-based child care, Morisset 4 Stockton Street Morisset 2264 Lake Macquarie Construction certificate issued $2.8m $302k – $468k
68 School, Lochinvar 52 Wyndella Road Lochinvar 2321 Maitland DA on public exhibition $21.7m $2.4m – $3.7m
56 Centre-based child care, Thornton 16 Portabello Crescent Thornton 2322 Maitland DA — info requested $1.8m $198k – $306k

Infrastructure 2 shown

ScoreProjectCouncilStage CostElectrical est.Builder
72 6-lot subdivision, Floraville 119 Floraville Road Floraville 2280 Lake Macquarie Development approved $633k $76k – $139k
66 Erection of a new structure, Maitland LGA 109 Mount Vincent Road, East Maitland, NSW Maitland DA — info requested $21.9m $2.6m – $4.8m

Residential 8 shown

ScoreProjectCouncilStage CostElectrical est.Builder
91 Residential flat building, Nelson Bay 90 Magnus Street Nelson Bay 2315 Port Stephens Construction certificate issued $5.5m $327k – $545k HPAC PTY LTD
74 Dwelling house, Warners Bay 91 Warners Bay Road Warners Bay 2282 Lake Macquarie Construction certificate issued $2.0m $120k – $200k Graph Builders Pty Ltd
69 Dwelling house, Stockton 144 Fullerton Street Stockton 2295 Newcastle Construction certificate issued $950k $57k – $95k INSITU BUILDING CO PTY LTD
69 Dwelling house, Charlestown 5 Mimosa Avenue Charlestown 2290 Lake Macquarie Construction certificate issued $630k $38k – $63k MCDONALD JONES HOMES
69 Subdivision, North Lambton 65 George Street North Lambton 2299 Newcastle Construction certificate issued $596k $36k – $60k MASTERTON HOMES PTY LIMITED
69 Dwelling house, Georgetown 18 Mabel Street Georgetown 2298 Newcastle Construction certificate issued $500k $30k – $50k JOCK ARMSTRONG
68 Multi-dwelling housing (23 dwellings), Elermore Vale 142 Cardiff Road Elermore Vale 2287 Newcastle DA under assessment $12.7m $765k – $1.3m
68 29-lot subdivision, Cessnock 34 Government Road Cessnock 2325 Cessnock Development approved $2.7m $108k – $243k

Big applications, early stage

10 projects over $3m

Nothing to quote here for months. It is on the list because the cheapest lead you will ever get is the one you knew about before the builder was appointed. One introduction email now.

ScoreProjectCouncilStage CostElectrical est.Builder
68 School, Lochinvar 52 Wyndella Road Lochinvar 2321 Maitland DA on public exhibition $21.7m $2.4m – $3.7m
68 Multi-dwelling housing (23 dwellings), Elermore Vale 142 Cardiff Road Elermore Vale 2287 Newcastle DA under assessment $12.7m $765k – $1.3m
66 Erection of a new structure, Maitland LGA 109 Mount Vincent Road, East Maitland, NSW Maitland DA — info requested $21.9m $2.6m – $4.8m
65 General industry, Heatherbrae 18 Kierman Circuit Heatherbrae 2324 Port Stephens DA on public exhibition $15.0m $1.5m – $2.7m
65 General industry, Williamtown 31 Aerospace Avenue Williamtown 2318 Port Stephens DA on public exhibition $10.9m $1.1m – $2.0m
63 Demolition, Kahibah 101 Wallsend Street Kahibah 2290 Lake Macquarie Development approved $3.9m $234k – $390k
62 Multi-dwelling housing (26 dwellings), Toronto 163 Excelsior Parade Toronto 2283 Lake Macquarie DA — info requested $6.5m $390k – $650k
61 473-lot subdivision, Bellbird Heights 254 Wollombi Road Bellbird Heights 2325 Cessnock DA — info requested $69.7m $2.8m – $6.3m
60 Tourist and visitor accommodation, Newcastle 110 Scott Street Newcastle 2300 Newcastle DA — info requested $7.5m $755k – $1.2m
57 31-lot subdivision, Wyee 1487 Hue Hue Road Wyee 2259 Lake Macquarie DA under assessment $4.0m $159k – $358k

Builder watchlist

top 15 by tracked value

This is the part no council website will give you. Construction certificates name the building company, so over time you can see who is actually building in the Hunter and how much of it. Treat this as your target account list: winning one relationship here is worth more than fifty cold quotes.

#BuilderTracked valueJobs New this fortnightLargest tracked project
01 BLOC CONSTRUCTIONS (NSW) PTY LIMITED Newcastle $233.5m 1 0 Mixed use development (351 dwellings), Newcastle West$233,534,640
02 SOUTHERN CROSS ELECTRICAL ENGINEERING LIMITED Newcastle $208.0m 1 0 Electricity generating facility (non-solar or wind), Mayfield West$208,000,000
03 GWH BUILD PTY LTD Newcastle $109.8m 4 2 Mixed use development (280 dwellings), Newcastle West$80,300,000
04 MAINBRACE CONSTRUCTIONS (NSW) PTY LTD Lake Macquarie $29.3m 1 0 Retail Premise, Belmont North$29,259,826
05 Patterson Building Group Pty Limited Newcastle $20.5m 1 0 Seniors housing (40 dwellings), Shortland$20,519,856
06 SNL Building Constructions Pty Ltd Lake Macquarie, Newcastle $18.6m 4 0 Multi-dwelling housing (38 dwellings), Waratah West$13,348,214
07 Graph Builders Pty Ltd Lake Macquarie $16.2m 4 1 Erection of a new structure, Cooranbong$5,829,334
08 MCDONALD JONES HOMES Cessnock, Lake Macquarie, Maitland, Port Stephens $15.5m 28 4 Dwelling house, Mulbring$918,530
09 BROWN COMMERCIAL BUILDING PTY LIMITED Lake Macquarie, Maitland, Newcastle $14.9m 4 1 Centre-based child care, Lochinvar$4,865,604
10 EDEN BRAE HOLDINGS PTY LIMITED Cessnock, Lake Macquarie, Maitland, Newcastle $10.1m 21 10 Dwelling house, Speers Point$795,846
11 MONTGOMERY HOMES PTY LTD Cessnock, Lake Macquarie, Maitland, Newcastle, Port Stephens $9.4m 13 2 Dwelling house, Nelson Bay$1,130,338
12 MCDONALD JONES COMMUNITIES PTY LIMITED Cessnock, Maitland $8.4m 23 6 2-lot subdivision, Cessnock LGA$577,605
13 CLARENDON HOMES (NSW) PTY LTD Cessnock, Lake Macquarie, Maitland $8.1m 10 2 Subdivision, Warners Bay$978,214
14 DECODE CONSTRUCTION PTY LTD Newcastle $7.7m 2 1 Shop top housing, Newcastle West$6,565,956
15 MOJO HOMES PTY LIMITED Cessnock, Lake Macquarie, Maitland, Newcastle, Port Stephens $7.2m 10 1 Secondary dwelling, Cameron Park$1,046,930

Where to point the ute

top 12 suburbs
Busiest suburbs this fortnightVerified construction value, then number of projects. Useful for planning a run of site visits in one trip.
Morisset Park$463.2m · 3Newcastle West$87.0m · 4Bellbird Heights$69.7m · 1Address not supplied$67.3m · 87Lochinvar$39.9m · 35Rutherford$20.2m · 11Merewether$19.3m · 31Heatherbrae$16.3m · 7Chisholm$14.8m · 24Elermore Vale$14.7m · 4Edgeworth$12.6m · 24Nelson Bay$12.4m · 16

The public pipeline

$6.4bn of funded work

State and federally funded Hunter work does not appear in council development application data, because it runs through separate approval pathways. This section is compiled by hand from the NSW Budget papers and agency announcements. These are the jobs that will still be going in three years.

Hunter-Central Coast Renewable Energy Zone network infrastructure

up to $3.9bn private investment
Where Upper Hunter to Central Coast, incl. Newcastle, Lake Macquarie, Port Stephens Stage Construction from early 2026 Source EnergyCo NSW

Ausgrid selected to design, build, finance, operate and maintain. Adds 1 GW of transfer capacity by 2028. Includes 85 km of sub-transmission line Kurri Kurri to Muswellbrook and 18 km of underground fibre. Forecast average 590 direct construction jobs a year.

What it means for an electricianHV transmission and sub-transmission, substations, protection and control, comms and fibre, construction power. Tier-1 principal contractors — target subcontract packages, not the head contract.

John Hunter Health and Innovation Precinct

$890.0m
Where New Lambton Heights, Newcastle Stage Funded, delivery underway Source NSW Budget 2026-27, Hunter regional paper

Largest single health capital allocation in the region.

What it means for an electricianEssential services, UPS and standby generation, AS/NZS 3003 body-protected areas, nurse call, medical gas alarms, data density, specialist lighting, security and access control.

Belmont Desalination Plant

$530.0m
Where Belmont, Lake Macquarie Stage Design and construction funded Source NSW Budget 2026-27, Hunter regional paper

Hunter Water's permanent desalination capacity.

What it means for an electricianHV supply and substation, MCCs and VSDs for high-pressure pumping, SCADA and instrumentation, hazardous-area work, standby generation.

M1 Pacific Motorway extension to Raymond Terrace

$390.5m (2026-27 allocation)
Where Black Hill to Raymond Terrace Stage Under construction Source NSW Budget 2026-27, Hunter regional paper

Includes new bridges over the Hunter River.

What it means for an electricianRoad and high-mast lighting, ITS and variable message signage power, communications pits and conduit, tunnel/underpass services.

Muswellbrook bypass

$258.2m (2026-27 allocation)
Where Muswellbrook (Upper Hunter — outside core coverage, watch item) Stage Works underway Source NSW Budget 2026-27, Hunter regional paper

Upper Hunter corridor upgrade programme.

What it means for an electricianRoad lighting, intersection and signal power, comms infrastructure.

Cessnock Hospital redevelopment

$138.0m
Where Cessnock Stage Redevelopment funded Source NSW Budget 2026-27, Hunter regional paper

Full hospital redevelopment in the coverage area.

What it means for an electricianEssential and standby supply, body-protected wiring, nurse call, theatre and imaging power, data, security.

Singleton bypass

$119.1m (2026-27 allocation)
Where Singleton (Upper Hunter — watch item) Stage Construction Source NSW Budget 2026-27, Hunter regional paper

New Hunter River crossing and bypass alignment.

What it means for an electricianRoad lighting, signals, comms.

Nelson Bay Road upgrade

$87.4m (2026-27 allocation)
Where Williamtown to Bobs Farm, Port Stephens Stage Construction Source NSW Budget 2026-27, Hunter regional paper

Duplication through the Williamtown defence and aerospace corridor.

What it means for an electricianRoad lighting, intersection power, service relocations, comms conduit.

Flood management asset repairs, Hunter

$73.1m
Where Across the Hunter valley Stage Programme of works Source NSW Budget 2026-27, Hunter regional paper

Critical repairs to damaged flood management assets — many small discrete packages rather than one head contract.

What it means for an electricianPump station power and controls, telemetry, switchboards, standby generation. Well suited to mid-size local contractors.

Maitland Integrated Community and Community Mental Health Service

$22.0m
Where Maitland Stage Funded Source NSW Budget 2026-27, Hunter regional paper

Plus $7.5m for the Maitland Hospital car park.

What it means for an electricianConsulting-suite power and data, nurse call/duress, lighting controls, car park lighting and EV provision.

Broadmeadow precinct and Newcastle Entertainment Centre planning

$14.0m (planning)
Where Broadmeadow, Newcastle Stage Planning and business case Source NSW Budget 2026-27, Hunter regional paper

Early planning money for a precinct expected to generate a very large construction programme. Worth tracking now, not quoting.

What it means for an electricianNothing to quote yet. The value of knowing early is relationship building with the delivery agencies and shortlisted designers.

Net Zero Manufacturing Centre of Excellence, TAFE NSW Tighes Hill

Funded (amount not itemised)
Where Tighes Hill, Newcastle Stage Funded Source NSW Budget 2026-27, Hunter regional paper

TAFE facility tied to the region's energy transition training pipeline.

What it means for an electricianTraining-rig power, three-phase distribution, workshop lighting, solar and battery training installations, data.

How this report is made

method and limits

Where the data comes from

Every council project in this report is drawn from the NSW Planning Portal's ePlanning open data feeds, published by the NSW Department of Planning, Housing and Infrastructure under a Creative Commons Attribution licence and refreshed daily. We pull three separate feeds:

  • Development applications — the pipeline, typically 6 to 24 months before anyone picks up a tool.
  • Complying development certificates — fast-tracked work that can start almost immediately.
  • Construction certificates — the strongest signal there is. A certificate means the job is about to be built, and it often names the building company.

Records for the same address across all three feeds are merged into one project so you see a single entry with its history, not the same job three times.

How the score works

Each project is scored out of 100 from five inputs: the kind of development, how far through approval it is, the declared cost, the distance from Newcastle, and specific high-intent signals such as a named builder, a large dwelling count, or solar and EV scope in the application. Sector and stage do most of the work — a construction certificate for a medical centre outranks a much larger development application for a subdivision, because one needs an electrician in a fortnight and the other in two years.

What is fact and what is our estimate

Fact, straight from the government feed: the address, the development type, the approval stage and dates, the declared cost of development, the dwelling and lot counts, the floor area, the building code class, and the builder's name where a certificate records it.

Our estimate, not a quote: the opportunity score, the electrical share of the cost, the likely scope of works, and the suggested timing. The electrical percentages are industry rules of thumb applied to a declared cost. Use them to rank where to spend your week, never to price a job.

Data quality

Declared costs on planning applications are entered by applicants and are not audited, so the raw feed contains obvious errors — this fortnight it included a two-dwelling development in Nelson Bay lodged at $1.375 billion. We cross-check every figure against floor area, dwelling count and lot count where the feed supplies them.

  • 87% of costs passed a plausibility cross-check.
  • 58 records were flagged as implausible or uncorroborated. They are still listed, because the project is real, but the dollar figure is marked and excluded from every total in this report.
  • 106 records lodged no cost at all.

What this report cannot tell you

  • Who holds the electrical package. A named builder is a door, not a contract.
  • Whether a job is already let. Always ask.
  • Private work under the certificate threshold, or maintenance and service work, which never appears in planning data at all.

Verify before you quote

Every entry carries its NSW Planning Portal reference and, where available, the council's own application number. Before you price anything, look the reference up on the council's DA tracker to confirm the current status. Approvals get modified, withdrawn and appealed, and this report is a snapshot dated 10 September 2026.

Sources and licence. Council development data: NSW Planning Portal ePlanning open data APIs, © State of New South Wales (Department of Planning, Housing and Infrastructure), used under a Creative Commons Attribution 4.0 licence. Public pipeline figures: NSW Budget 2026-27 regional papers, EnergyCo NSW, and the sources cited against each item. Not financial or contractual advice. Tradiesignal aggregates public records and applies its own scoring. Figures described as estimates are estimates. Verify every project against the primary source before committing time or money.

You just read a fortnight of the Hunter's construction pipeline.

This lands in your inbox every Monday at 6am, filtered to your patch and your sectors. Fourteen days free, no card, cancel by replying to any email.

Start free trial How it works

Know a sparky who'd use this? Forward it — if they subscribe you both get a month free.